Civil Transactions Law Saudi Arabia: Guide for Business Contracts

November 22, 202611 min readLegal Insights

Summary

  • Saudi Arabia's Civil Transactions Law (Royal Decree M/191) has been in force since December 2023 and applies to commercial transactions where no specific provision exists and to the extent consistent with their nature (Clause Sixth of the decree).
  • The Law applies to events before it took effect, unless a party relies on a conflicting provision or judicial principle, or a limitation period had already started (Clause Fifth).
  • Penalty clauses are allowed unless the obligation is a sum of money (Article 178); the court may reduce an excessive amount or increase it for fraud or gross fault, and parties cannot contract out of this (Article 179).
  • Compensation covers actual loss and lost profit (Article 137), but in contract it is limited to damage foreseeable at signing unless there is fraud or gross fault (Article 180).
  • The hardship rule in Article 97 is mandatory. The general limitation period is 10 years (Article 295), but claims within the commercial court's jurisdiction are not heard after 5 years from when the right arose, absent a specific provision (Article 24 of the Commercial Courts Law), and the parties cannot shorten or extend the Civil Transactions Law period (Article 305).

The Civil Transactions Law is Saudi Arabia's general code for contracts, obligations and compensation. It was issued by Royal Decree No. M/191 dated 29/11/1444H, published on 19 June 2023, and came into force 180 days after publication, in December 2023. Because it applies to commercial transactions wherever the commercial laws contain no specific provision, it now governs much of the supply, construction, services and distribution contracts that companies sign in the Kingdom. This guide explains what the Civil Transactions Law Saudi Arabia adopted in 2023 means for business contracts in practice: formation and interpretation, penalty clauses, compensation for damage, force majeure and exceptional circumstances, limitation periods, and its effect on contracts signed before it took effect, based on the text published by the Bureau of Experts at the Council of Ministers as of November 2026.

What is the Civil Transactions Law and when did it take effect?

The Civil Transactions Law is a codified statute of 721 articles covering the sources of obligations (contract, harmful act and unjust enrichment), their effects, transfer and extinction, the named contracts such as sale, lease and construction (muqawala), and a closing set of general rules. It applies 180 days after its publication in the Official Gazette (Article 721), and the Bureau of Experts lists its status as "in force".

Article 1 sets the order of reference: the Law's provisions apply to every matter they address in wording or in substance; where no provision applies, the general rules in the final provisions apply (Article 720), and then the rules of Islamic Sharia most consistent with the Law. Its application does not prejudice specific statutory provisions. Contract questions that used to be answered mainly through judicial discretion now have written rules that businesses can anticipate and plan around.

Does the Civil Transactions Law apply to commercial contracts between companies?

Yes. Clause (Sixth) of Royal Decree M/191 applies the Law to commercial transactions to the extent consistent with the nature of commercial dealings, and where the commercial laws contain no specific provision. The Law is the general rule; special laws such as the Companies Law and the Commercial Courts Law prevail on the matters they regulate.

Under Clause (Fourth) of the decree, the Law also does not prejudice treaties and agreements the Kingdom is party to, the jurisdiction of public or judicial bodies, or statutory registration, recording and licensing procedures. The commercial courts hear disputes arising from the partnership (musharaka) contracts regulated by the Law, after the same decree amended paragraph (3) of Article 16 of the Commercial Courts Law. Jurisdiction and procedure are covered in our guide to filing a case in the Saudi commercial court.

Does the Law apply to contracts signed before December 2023?

As a rule, yes. Clause (Fifth) of the decree applies the Law to all events that occurred before it took effect, with two exceptions:

  1. Where a statutory provision or judicial principle relating to the event conflicts with the Law and one of the parties relies on it.
  2. Where the matter concerns a limitation period (time bar on hearing a claim) that started running before the Law took effect.

In practice, a contract signed in 2021, for example, is not automatically exempt because it predates the Law, but a party relying on a conflicting earlier judicial principle must actually invoke it in its defence. A limitation period that began before December 2023 stays outside the Law. Long-term contracts signed before the Law therefore deserve review rather than an assumption that the Law does not touch them.

How is a contract formed, and what are the risks in negotiations?

A contract is formed when an offer is matched by an acceptance to produce a legal effect (Article 31). Offer and acceptance may be expressed by anything that shows intent: words, writing, an understood gesture or conduct, expressly or impliedly, unless the law, the agreement or the nature of the dealing requires otherwise (Article 33). An exchange of letters or emails can therefore form a contract before the final version is signed.

Rules that matter to procurement and sales teams:

  • Qualified acceptance: any modification in an acceptance is a rejection containing a new offer (Article 36).
  • Silence: it is not acceptance unless agreed or indicated by circumstances, and it counts as acceptance where the parties have prior dealings and the offer relates to them (Article 37).
  • Non-essential terms: if the parties agree on the essential terms and defer the rest, the contract is formed and the court fills the gaps under the law, the nature of the dealing and custom, unless the parties made formation conditional on that later agreement (Article 42).
  • Negotiations: they do not oblige anyone to conclude the contract, but a party that negotiates or breaks off negotiations in bad faith is liable for the resulting damage, excluding the profit expected from the contract. Bad faith includes lack of seriousness or deliberately withholding a material fact (Article 41).
  • Promise to contract: it is binding only if the essential terms and the period for concluding the contract are specified (Article 43). This matters for letters of intent and memoranda of understanding.

So state expressly whether a letter of intent is binding, and make formation conditional on signing the final document if that is what the company intends.

How do Saudi courts interpret contract terms?

If the wording of a contract is clear, it may not be departed from on the pretext of interpretation. Where interpretation is needed, the court looks for the common intention of the parties rather than the literal meaning alone, guided by custom, the circumstances, the nature of the dealing and the parties' prior course of dealing, and reads the terms in light of each other (Article 104).

Three rules work against whoever drafted the contract loosely:

  • Doubt is resolved in favour of the party bearing the obligation or condition, and in adhesion contracts in favour of the adhering party (Article 104).
  • Abusive terms in adhesion contracts may be modified by the court, or the adhering party exempted from them, and any agreement to the contrary is void (Article 96). Standard terms a company imposes on customers without negotiation are more exposed to this rule.
  • Good faith and implied obligations: a contract must be performed in good faith and covers not only its express terms but what follows from it under the law, custom and the nature of the contract (Article 95). Among the general rules: "what is customary is as if stipulated" (Article 720).

An invalid condition is void on its own, and a party may seek annulment of the whole contract if it would not have agreed to it without that condition (Article 74).

How do penalty clauses work, and can the court adjust them?

A penalty clause (agreed compensation, al-shart al-jaza'i) is an amount the parties fix in advance, in the contract or a later agreement, as compensation for breach. Article 178 permits it unless the obligation is a sum of money, and no prior notice (i'dhar) is needed to claim it. Article 179, however, gives the court power to adjust it in three situations, and any agreement to the contrary is void:

SituationWho asksEffectBasis
The debtor proves the creditor suffered no damage at allDebtorAgreed compensation is not dueArticle 179
The amount is excessive or the obligation was partly performedDebtorThe court may reduce itArticle 179
Damage exceeds the agreed amount due to the debtor's fraud or gross faultCreditorThe court may increase it up to the damageArticle 179
The obligation is a sum of money (such as price or rent)The text does not permit pre-agreed compensationArticle 178

Example: a SAR 2,000,000 supply contract sets a delay penalty of 1% per week capped at 10%. The supplier is 10 weeks late, so the penalty reaches SAR 200,000. The buyer may claim it without prior notice (Article 178). The supplier may ask the court to reduce it if it proves the amount is excessive compared with the actual damage, or resist it entirely if it proves the buyer suffered no damage. The court decides based on the evidence each side presents.

In practice, a penalty clause under the Law is not a guaranteed sum but a presumption of damage that shifts the burden of proof to the debtor. Keep evidence of actual loss (replacement costs, penalties the company paid its own customers, documented lost profit). For monetary obligations such as late invoice payment, safer tools are covered in our guide to avoiding commercial disputes through contract drafting.

How is compensation for damage and lost profit calculated?

Compensation for damage under the Law must make good the whole damage, restoring the injured party to the position it was in, or would have been in, had the damage not occurred (Article 136). It covers the loss suffered and the profit lost where they are a natural result of the act, meaning the injured party could not have avoided them through reasonable effort (Article 137).

For contracts specifically, if compensation is not fixed in the contract or by law, the court assesses it under Articles 136 to 139, but a debtor who committed no fraud or gross fault is liable only for damage that could normally have been foreseen when the contract was made (Article 180). Unforeseeable damage at signing is compensated only in cases of fraud or gross fault.

Other rules that affect the amount:

  • Creditor's fault: if the creditor contributed to or increased the damage, its right is lost wholly or partly in proportion (Articles 172 and 128).
  • Notice (i'dhar): compensation is due only after the debtor is formally notified, unless an agreement or law provides otherwise (Article 175). Notice may be given by any agreed means or any statutory means of service, including filing a claim (Article 177). It is not needed in cases including where the parties agreed the debtor is in default once the due date passes, or where the debtor states in writing that it will not perform (Article 176).
  • Exclusion and limitation of liability: the parties may exempt the debtor from compensation for non-performance or delay of a contractual obligation, except for fraud or gross fault, but liability for a harmful act cannot be excluded (Article 173).
  • Negotiations and withdrawn offers: compensation in these cases excludes the profit expected from the contract (Articles 35 and 41).

What is the difference between force majeure and exceptional circumstances under the Law?

The difference lies in the outcome: force majeure makes performance impossible, so the obligation ends; exceptional circumstances make it onerous, so the obligation stays but may be reduced to a reasonable level.

IssueImpossibility (force majeure)Exceptional circumstances (hardship)
ConditionPerformance becomes impossible for a cause beyond the debtor's controlGeneral exceptional circumstances that could not be foreseen make performance onerous, threatening a grave loss
EffectThe obligation and the counter-obligation end and the contract is dissolved by operation of law (Article 110)The debtor invites the other party to negotiate without unjustified delay, then the court may reduce the onerous obligation to a reasonable level (Article 97)
Partial or temporary impossibilityOnly the impossible part and its counterpart end, including temporary impossibility in contracts performed over time (Article 110)Not applicable
Suspending performanceNo obligation remainsA request to negotiate does not entitle the debtor to stop performing (Article 97)
Contracting outThe debtor may agree to bear the risk of force majeure (Article 174)Any agreement contrary to Article 97 is void

On compensation, a debtor is not liable for non-performance if it proves the failure was due to a cause beyond its control (Article 170), nor for delay if it proves the delay had such a cause (Article 171).

The drafting impact is direct: a force majeure clause can widen or narrow the triggering events or place the risk on the debtor, but a clause waiving the debtor's right to rely on exceptional circumstances has no effect. Construction contracts also have a specific rule in Article 471 on the collapse of contractual balance due to general exceptional circumstances.

What are the limitation periods under the Civil Transactions Law?

The right itself does not lapse with time, but a claim is not heard against a denying defendant after 10 years, unless another statutory provision applies (Article 295). The period runs from the day the right becomes due (Article 299), and periods under the Law are calculated by the Hijri calendar (Article 2).

Article 295 itself, however, excludes cases governed by another statutory provision, and the Commercial Courts Law is such a provision: absent a specific provision, claims within the commercial court's jurisdiction are not heard after 5 years from the date the claimed right arose, unless the defendant acknowledges the right or the claimant presents an excuse the court accepts (Article 24). Where a dispute between two companies is commercial and falls within the commercial court's jurisdiction, the prudent course is to plan on 5 years, not 10.

Type of rightPeriodBasis
General rule10 yearsArticle 295
Fees of liberal professionals (doctors, lawyers, engineers), and periodic recurring rights such as real estate rent5 yearsArticle 296
Merchants' claims for goods and services supplied to persons who do not trade in them1 yearArticle 297
Compensation claim for a harmful act (tort)3 years from knowledge of the damage and the person liable, and at most 10 years from its occurrenceArticle 143
Claims within the commercial court's jurisdiction, absent a specific provision5 years from when the right aroseArticle 24, Commercial Courts Law

Civil Transactions Law rules that matter for managing claims:

  • Suspension: the period is suspended whenever an excuse prevents a claim, including good-faith negotiations ongoing when the period ends (Article 300).
  • Interruption: by the debtor's express or implied acknowledgement, by a court claim even before a court without jurisdiction, or by any other judicial step (Article 302), after which, as a rule, a new period equal to the first starts, or 10 years where a court judgment has been issued on the right (Article 304).
  • No contractual change: the parties may not agree to shorten or extend the period (Article 305). A clause saying "no claim may be brought after 6 months" does not change the limitation period.

For money claims between companies, see also our guide to commercial debt recovery tools.

What should companies review in their existing contracts?

A practical checklist for supply, services, construction and distribution contracts, new and existing:

  1. Identify the contracts that matter: long-term, high-value contracts, and those signed before December 2023 that are still running, since the Law applies to them as a rule.
  2. Review penalty clauses: is the amount proportionate to a provable loss? Does it attach to a monetary obligation that Article 178 does not cover? Does the cap have a clear commercial logic?
  3. Review liability caps: carve out fraud and gross fault expressly (Article 173), and define excluded indirect loss and lost profit precisely.
  4. Separate force majeure from hardship: define the events, notice and timelines in the force majeure clause, and do not rely on excluding Article 97, because that is void.
  5. Regulate notice: specify the means of notice (a designated email or national address), decide whether the debtor is in default once the due date passes (Articles 176 and 177), and whether termination without a court order applies with an express waiver of notice (Article 108).
  6. Check clarity: remove conflicts between clauses and schedules, since doubt favours the obligor and, in adhesion contracts, the adhering party (Article 104).
  7. Review standard terms: abusive terms in adhesion contracts can be modified by the court (Article 96).
  8. Document negotiations: state expressly the nature of letters of intent and memoranda of understanding (Articles 41 and 43).
  9. Track claim periods: record when each right becomes due, and do not rely on a clause that shortens or extends the period (Article 305).
  10. Check special laws: the Companies Law, the Commercial Courts Law and sector regulations prevail on the matters they regulate. In acquisitions, this review is part of legal due diligence for companies.

Practice note

Many contracts used by companies in Saudi Arabia are translated international templates, drafted on the assumption that a penalty clause is a fixed, non-negotiable sum and that the force majeure clause covers any price or supply disruption. The Civil Transactions Law changes both assumptions: penalty clauses can be reduced or increased under a mandatory rule, hardship is not impossibility, and the hardship rule cannot be excluded. Reviewing the company's approved templates once, and aligning their compensation, notice and force majeure clauses, is usually cheaper than dealing with each contract when a dispute arises.

The Dispute Resolution team at Faisal Siddiqui Law Firm can review a company's existing contracts and templates under the Civil Transactions Law and represent it in the claims that arise from them.

Frequently Asked Questions

Does the Civil Transactions Law apply to companies and commercial contracts?

Yes. Clause (Sixth) of Royal Decree M/191 applies the Law to commercial transactions to the extent consistent with their nature, wherever the commercial laws contain no specific provision. If the Companies Law or the Commercial Courts Law regulates a matter, its text prevails; anything left unregulated falls back on the Civil Transactions Law, then the general rules, then the Sharia rules most consistent with the Law (Article 1).

Can a Saudi court reduce a penalty clause?

Yes. Article 179 allows the court, at the debtor's request, to reduce agreed compensation if the debtor proves it is excessive or that the obligation was partly performed, and it is not due at all if the debtor proves the creditor suffered no damage. At the creditor's request, the court may increase it up to the actual damage where fraud or gross fault caused a larger loss. Any agreement to the contrary is void.

Does compensation for damage include lost profit?

Yes. Article 137 measures damage by the loss suffered and the profit lost where they are a natural result of the act. In contractual obligations, however, a debtor who committed no fraud or gross fault is liable only for damage that could normally have been foreseen when the contract was made (Article 180). Compensation for bad-faith negotiations excludes the profit expected from the contract (Article 41).

What is the difference between force majeure and exceptional circumstances under the Law?

Force majeure makes performance impossible for a cause beyond the debtor's control, so the obligation and counter-obligation end and the contract dissolves automatically (Article 110); the debtor may agree to bear that risk (Article 174). General unforeseeable exceptional circumstances make performance onerous: the debtor must request negotiation without suspending performance, then the court may reduce the obligation to a reasonable level, and this cannot be excluded by contract (Article 97).

Does the Civil Transactions Law apply to contracts signed before it took effect?

As a rule, yes. Under Clause (Fifth) of the decree, the Law applies to all events that occurred before it took effect, with two exceptions: a conflicting statutory provision or judicial principle relating to the event that one of the parties relies on, or a limitation period that began running before the Law took effect. Contracts signed earlier and still running therefore need review.

Can a contract shorten the period for bringing a claim?

No, under the Civil Transactions Law. Article 305 prohibits agreements that shorten or extend the limitation period, and a debtor cannot waive the right to rely on it before that right arises. The general period is 10 years (Article 295), with shorter periods for specific rights, and 5 years for claims within the commercial court's jurisdiction absent a specific provision (Article 24 of the Commercial Courts Law). Article 24 does not address agreements to change that period, so do not build a contract on shortening it.